In
support of the project architect, Cullinan performed civil / site engineering for this new
high school project. Project tasks include site design for new building with ancillary
parking and athletic fields, design of sewer ejection station, design of sewer connection
for existing school, design relocation of existing drain, permitting (local, Wetlands NOI,
and DEP sewer connection permit), and construction administration. Phase II of the project
will include site design for play fields, permitting (local, Wetlands NOI, Army Corps,
easement, and ENF), and construction administration. |